Question : How PeopleSoft Does Calculates Holiday Hours during Paysheet Creation?
Answer:
You setup Holiday Calendar with holiday hours as shown in the below screen shot. For Example for New Year, the holiday hours are set as 8 Standard Hours.
If you are using Payroll for North America for US, you will select Standard as the Holiday Type as this value designates a U.S. holiday.
In this example , I am assuming that you are using Holiday Hours to be controlled by HR Paygroups and Job (not through Time & Labor Rules). Also you are using Semi Monthly Payroll as shown below :
Now, let’s say that you have the 2 Job Codes , one for Full Time Employee and another for Part Time employee with Standard Hours Set to 86.67 for each of this job codes and Semi Monthly as the Work Period.
Part Time Job Code Setup: